Problem:

You have make changes to the material overhead on the BOM and the capacity overhead of one machine center but the cost is not reflected in standard Unit Cost yet.

Solution:

You need to run the Calc. Standard Cost function at the Item Card.

Discussion:
  1. On Item Card, Click Manufacturing --> Calc. Standard Cost.
  2. In the next window, click Single / All Levels and then click OK.
Once you click on the OK button, Navision will recalculate the standard cost again based on the material and machince overhead cost.